Being built: 2085 Skyline Crt and 2088 Skyline Crt, Brentwood, Burnaby. Timeline and latest steps from City of Burnaby records.

← All Brentwood developments
Being built
Asked
Council
Approved
Building
Done

What this means: The city has issued a building permit, so crews can build.

Stage as of Sep 28, 2026 (the city stopped publishing this permit data)

2phases
Jun 8, 2020last change

SOLO District at 2085 Skyline Crt and 2088 Skyline Crt in Brentwood, Burnaby, is being built. The latest step was on Jun 8, 2020: council approved the rezoning. City records don't give a completion date.

Timeline

Every step we know of, newest first.

  1. 🏛️

    Council approved the rezoning. Source

  2. 📝

    Development application made to the city. Source

  3. 📝

    Development application made to the city. Source

  4. 🏛️

    Council approved the rezoning. Source

The plans

Being built 2085 Skyline Crt

Permit changes to the approved CD zoning for the final phase of SOLO District (Phase 2, Lots C & D) 10/12/2019 Lot C is 2085 Skyline Lot D is 2088 Skyline. Lot C is under construction. Phased work for two separate towers sharing one underground structure when complete. KOC

Rezoning REZ15-00015
Being built 2088 Skyline Crt

SOLO Phase 4 (tower C) amend plan for additional office levels and additional parking

Rezoning REZ20-00005

Nearby developments